September 2026 Capital Project Update

New Classrooms and Playground Take Shape

September brought continued progress on Beekmantown Central School District’s Capital Improvement Project. Crews advanced exterior finishes, classroom construction, bathroom improvements, and the building systems that will serve the new addition.

Visible milestones included new windows installed on the south wall of the classroom addition, completed ceramic tile installation in the new bathrooms, and installation of the addition’s roof system. The playground also moved closer to completion, with the September 30 report identifying the area as approximately 90% complete, with turf installation remaining.

Project Highlights

  • Exterior work advances — Crews are installing brick on the north wall, and windows have been installed on the south wall of the new addition.

  • Classroom interiors take shape — Construction of classroom block walls continues, along with drywall installation along the exterior walls inside the new classrooms.

  • Bathroom tile completed — Ceramic tile installation is finished in the new bathrooms.

  • Playground nears completion — The playground fence has been installed, while grading and drainage work continues. Turf installation remains.

  • Roof system installed — The new addition’s roof system is in place, and connections to the existing roof have been made. Roof trim still needs to be finished.

  • Heating, cooling, and water systems progress — Crews are installing piping in the addition and have completed pipe insulation in the new bathroom areas.

  • Electrical connections advance — The electrical pathway from the basement to the addition is complete, and crews are installing wiring to supply power to the new spaces.

Exterior and Site Work

The new classroom addition continues to take shape as crews install exterior brickwork and build out the classroom walls. Newly installed south-facing windows mark another visible step toward finished learning spaces.

Roofing work also reached an important milestone this month. The new roof system has been installed and connected to the existing building, with finishing work on the roof trim still ahead.

Around the playground, crews are continuing to shape the ground and improve drainage. The fence has been installed, and the report’s photographs show rubber playground surfacing, curbs, and progress around the play equipment. As of September 30, the playground area was approximately 90% complete, with turf still to be installed.

Plumbing, Heating, Cooling, and Electrical Systems

Behind the walls, crews are installing the systems that will make the new classrooms ready for daily use.

Water supply lines are being installed in the addition, along with piping for heating and cooling. Supports for future ductwork are also in place, and plumbing and heating pipes in the bathroom areas have been insulated.

Electrical crews are installing protective pathways and electrical boxes within the classroom walls. They have completed the pathway from the basement to the addition and are pulling wires to the new electrical panel that will supply power to the new spaces.

The New Addition Is Taking Shape

September’s photographs highlight progress both inside and outside the building. Exterior finishes and windows are advancing, classroom walls are taking shape, bathroom tile is complete, and roof connections are in place.

Together, these improvements bring the project closer to providing finished classrooms and an updated playground for our students.

Building for the Future

Each month brings visible progress toward the district’s new learning and play spaces. We appreciate the continued patience and support of our students, families, staff, and community as this investment in Beekmantown’s facilities moves forward.

Check back regularly for additional construction updates and photos as the Capital Improvement Project continues.


September 2026 update


August 2026 Capital Project Update

Exterior Finishes and Building Systems Move Forward

August brought continued progress across several areas of Beekmantown Central School District’s Capital Improvement Project. Work on the new classroom addition is moving beyond the major structural phase, with crews now focusing on exterior finishes, classroom and bathroom construction, building systems, and site improvements.

One of the most visible changes this month was the installation of EIFS exterior finishing on the north and south ends of the new addition. Inside the building, crews completed partition walls for the new bathrooms and continued constructing block partition walls for the new classrooms. Kitchen work at both Cumberland Head Elementary School and the Middle/High School was also completed during the reporting period.

Project Highlights

  • Exterior finishes advancing — EIFS was installed on the north and south ends of the new classroom addition.

  • Classroom and bathroom construction continues — Bathroom partition walls were completed, while classroom block wall partitions continue to take shape.

  • Kitchen work completed — Work at both Cumberland Head Elementary School and the Middle/High School kitchens was completed during August.
  • Playground drainage and grading underway — Crews continued underground storm drainage installation along with grading and drainage improvements in the playground area.
  • New bathroom systems installed — Plumbing and heating-related work advanced in the new bathroom areas.
  • Electrical infrastructure expanded — Crews continued conduit and classroom rough-in work and installed a new electrical panel to serve the addition.
  • Plumbing upgrades completed — New bathroom plumbing, kitchen drain lines, grease trap work, and gas lines were completed during the reporting period.

 

Exterior and Site Work

Outside the new addition, work continued on the areas surrounding the playground. Crews are installing underground storm drainage while also completing grading and drainage improvements throughout the playground area.

The progress photos included in the August report show exterior finish work taking shape on the new wing, new brick work being installed around the playground-facing portion of the existing building, and significant grading activity throughout the courtyard and playground area.

Plumbing, Mechanical and Electrical Systems

Behind the walls, many of the systems that will support the new spaces are also taking shape.

Plumbing work for the new bathrooms has been completed, while crews have also installed the kitchen grease trap, drain lines, and new gas lines serving Cumberland Head and the Middle/High School kitchens. Mechanical crews installed heating-related plumbing in the new bathroom area and completed additional kitchen mechanical work.

Electrical crews are continuing rough-in work within the new classroom walls, running conduit from the basement to serve the addition, and have installed a new electrical panel to provide power to the new addition.

The New Addition Is Taking Shape

The photographs from August make the progress especially easy to see. Exterior walls are becoming enclosed and finished, bathroom plumbing and interior framing are advancing, electrical infrastructure is being installed, and site work is transforming the area around the new classroom wing.

With structural work largely behind us, the project is increasingly shifting toward the many exterior, interior, mechanical, plumbing, and electrical details that will turn the new addition into finished learning spaces for our students and staff.

Building for the Future

Each month, the new addition looks a little more complete and a little more connected to the existing campus. We appreciate the continued patience and support of our students, families, staff, and community as this important investment in Beekmantown’s facilities continues.

Check back regularly for additional construction updates and photos as the Capital Improvement Project moves forward.



  August 2026 Update


July 2026 Capital Project Update: New Classroom Addition Takes Shape

July brought one of the most visible milestones yet in Beekmantown Central School District's Capital Improvement Project. Structural steel for the new classroom addition has been installed, and the roof deck is now in place, giving the community a much clearer picture of the size and shape of the new space.

Inside the addition, crews have started constructing block partition walls for the new classrooms and are continuing work on exterior walls and the new bathroom area. Fireproofing is underway, and mechanical, plumbing and electrical systems are beginning to take shape throughout the new construction.

Project Highlights

  • Structural steel and roof deck installed: The framework and roof deck for the new classroom addition are now in place.

  • Classroom walls underway: Block partition walls have started in the new classroom spaces, along with exterior wall work beneath the windows.

  • Site work continues: Crews are installing underground storm drainage and completing grading and drainage work around the playground area.

  • Plumbing and mechanical work advancing: Roof drains are being installed in the addition, heating and cooling work is progressing in the bathroom area, and kitchen-related mechanical work has continued.

  • Electrical rough-in underway: Electrical crews are installing conduit and boxes in classroom block walls and running conduit through the basement to serve the new addition.

Progress in Photos

The July photos show how quickly the addition is changing. Steel framing now defines the new wing, classroom and exterior walls are taking shape, roof drainage piping is being installed, bathroom framing is progressing, and fireproofing has been applied in the new bathroom area.

What's Next?

Based on the work underway at the end of July, crews will continue classroom partition and exterior wall construction, mechanical/plumbing/electrical rough-in, site drainage and grading, and fireproofing and interior work. With structural framing complete, the project is moving into the next phase of enclosure and interior construction.

Building for the Future

The project remains on schedule. As construction continues, the new classroom addition is becoming more recognizable each week. These improvements represent a long-term investment in learning spaces that will serve Beekmantown students, staff and families for years to come.

For project updates, photos and information, visit BCSDK12.org/capital-project.

For a closer look at this month's progress, be sure to download the accompanying Capital Project Newsletter, which includes photographs and additional construction highlights.

 JuLY 2026 Update


June 2026 Construction Progress

Classroom Addition Takes Shape as Major Foundation Work Moves Forward

Beekmantown Central School District’s Capital Improvement Project continues to make visible progress, with important work advancing at both the main campus classroom addition and Cumberland Head Elementary School.

During the latest reporting period, crews completed the East and West foundation walls for the new classroom addition. Interior foundation backfilling has also been completed, and the concrete slab has been prepared, poured, and polished. This marks an exciting step forward as the project begins to move from below-ground foundation work toward a more recognizable building structure.

Site work is also continuing around the new addition. Crews are backfilling and compacting the area around the foundation and have started grading work for the future playground area. This work helps prepare the site for the next phases of construction and supports the long-term layout of the improved campus space.

At Cumberland Head Elementary School, progress continues on kitchen-related improvements. Work has included preparation for the new rooftop kitchen unit, installation of a roof curb, gas-line and vent-line work, and adjustments to kitchen lighting to support the mechanical work taking place.

Project Highlights

Major progress this month includes:

  • East and West foundation walls completed for the new classroom addition.
  • Interior foundation backfilling completed.
  • Concrete slab preparation completed.
  • Concrete slab poured and polished.
  • Backfilling and compaction continuing around the new addition.
  • Playground-area grading started.
  • Cumberland Head Elementary kitchen mechanical, plumbing, gas-line, vent-line, and electrical coordination moving forward.
  • Steel erection has started, helping the new addition begin to take shape above ground.

What’s Next?

In the coming weeks, work is expected to continue in several key areas:

  • Continued steel work for the new classroom addition.
  • Continued backfilling and compaction around the addition foundation.
  • Continued grading and site preparation near the playground area.
  • Ongoing mechanical, plumbing, gas-line, vent-line, and electrical work connected to the Cumberland Head Elementary kitchen upgrades.

Building for the Future

These improvements are part of Beekmantown Central School District’s ongoing commitment to maintaining and improving learning spaces for students, staff, and the community. As foundation work is completed and steel begins to rise, the classroom addition is becoming easier to see and understand as an investment in the future of our schools.

The District will continue to share updates as work progresses.

For a closer look at this month's progress, be sure to download the accompanying Capital Project Newsletter, which includes photographs and additional construction highlights.

 June 2026 Update


May 2026 Construction Progress

Exciting progress continues on Beekmantown Central School District's Capital Improvement Project as work advances on the new classroom addition. Over the past month, construction crews have reached several significant milestones that are laying the foundation for the next phase of work.

Project Highlights

  • North and South foundation walls completed
  • Interior support piers under construction
  • Foundation excavation continues
  • Underground storm drainage system installation underway
  • East foundation wall preparations in progress

The completion of the North and South foundation walls marks an important milestone, clearly defining the footprint of the future classroom addition. At the same time, crews continue to make steady progress installing underground infrastructure, constructing interior support piers, and preparing additional foundation walls as the project remains on schedule.

Current Progress

Foundation construction continues to move forward at a steady pace. Recent work has focused on completing major concrete foundation elements, installing critical underground storm drainage infrastructure, constructing interior structural supports, and preparing additional foundation wall sections. Each of these phases is essential to ensuring the long-term strength, safety, and durability of the new classroom addition.

As these foundational components are completed, the project is transitioning toward the next stages of structural construction, bringing the new learning spaces one step closer to reality.

What's Next?

Over the coming weeks, construction teams will continue:

  • Completing remaining foundation work
  • Installing additional structural supports
  • Expanding the site's underground drainage infrastructure
  • Preparing for the next phase of vertical construction

As work progresses throughout the summer, the community will begin to see the new classroom addition rise above ground, making the vision approved by district voters increasingly visible.

Project Status

🟢 Construction Progress: On Schedule

The project continues to advance according to the planned construction schedule, with work progressing safely and efficiently.

For a closer look at this month's progress, be sure to download the accompanying Capital Project Newsletter, which includes photographs and additional construction highlights.

 May 2026 Update